Tarago Road

  • Project typeCapital Works
  • Project valueInitial work $2.2 million. Rehabilitation/Repair works - $3m
  • Project scheduleTo be completed by 2025/26
Tarago Road showing road before work starts on Stage 1

We have received $3m from the NSW Government in February 2024 for rehabilitation and repair works on damaged sections of Tarago Road.

We will be targeting the worst sections of Tarago Road, with shoulder widening, rehabilitation and heavy patching.

There are six sections that are being upgraded. We have completed five of these sections.

Patch number 6 is the largest and is approximately 1/3 of the program and is being completed in the 2025-26 financial year. This work will include earthworks, road construction and guardrail, and follows on from the earlier construction work in 2022-2023.

Completed work

  • With the initial $2.2m in developer contribution funding, from mid-2022 to October-2023, we upgraded a 2km section starting just south of Mount Fairy Road and heading north on Tarago Road. It was completed in October 2023.
  • This included vegetation removal, road realignment, pavement rehabilitation, stormwater improvements and guardrail.
  • In 2023-24, three sections of stabilisation works were completed at an approximate cost of $800,000.
  • In 2024-25, two sections of stabilisation works were completed.

Location

Tarago Road, Mount Fairy 2580  View Map

Google Map