COMPLETED Queanbeyan Showground Pavilion

  • Project typeCapital Works
  • Project value$718,000 and $250,000 for internal works
  • Project scheduleTo be completed 2024
  • Contractor nameRice Constructions external pavilion
Exterior of showground pavilion Queanbeyan

This project was completed in November 2024.

The project is funded via a $100,000 contribution from Council, $18,000 raised by the Friends of the Showground and Jerrabomberra Rotary and a $600,000 contribution from the Stronger Country Community Fund.

Final approvals for the construction were received in June 2023. The contractors Rice Construction began work on the site mid August 2023. The main construction and exterior works were completed in May 2024

There is still further internal work to be completed. This includes toilet facilities, lighting, electrical and water and sewer services. An additional $250,000 has been allocated for this work.

You can download the final plans here(PDF, 2MB).