The Gidleigh Bridge replacement has now been completed and the new bridge commenced taking traffic on 13 May 2021.
It involves the replacement of the old timber bridge by a new INQUIK bridge which is part of the Council Bridge renewal program. The initial scope of the project includes the approach slabs and the sealing of both approaches (each 50m long). A further length may be sealed if budget permits.
Key elements of the Project
Project schedule (include times/days that the project will be worked on)
The construction will take place:
The only approved work that may take place outside of these hours includes:
Emergency safety work to reduce the risk of harm to staff, drivers, property, and environment
Gidleigh Lane, Bungendore 2621 View Map
Gidleigh Lane , Bungendore 2621
Old Gidleigh Bridge
Completed Gidleigh Bridge