Bedding Ground Creek bridge

  • Project typeCapital Works
  • Project value$1.406 million
  • Project scheduleCompleted March 2025
Bedding Ground Creek bridge

We replaced the old timber Bedding Ground Creek bridge on Reidsdale Road. This project was proudly funded by the NSW Government under Transport for NSW's Fixing Country Bridges program.

We began construction on 25 November 2024 and reopened the new bridge to traffic from late afternoon on Friday 7 March 2025.

The bridge and approaches were under worksite signage and reduced speed until they were sealed in mid-March 2025. The project is now complete.